Miami-Dade sets Nov. 18 ribbon cutting for South Dade bus center
The Homestead transit center is expected to begin operations Nov. 23 and support 100 articulated electric buses.
Key Takeaways
- •Miami-Dade scheduled the ribbon cutting for Nov. 18 and expects operations to begin Nov. 23.
- •The center will bring storage, charging, maintenance and operations for 100 articulated electric buses together.
- •The county says the facility will support more than 270 jobs; that is a projected figure.
Miami-Dade County has scheduled a Nov. 18 ribbon cutting for the South Dade Transit Operations Center in Homestead, with the facility expected to begin operations Nov. 23, according to the county's media advisory.
The center will bring storage, charging, maintenance and operations for a fleet of 100 articulated battery-electric buses into one location. Construction began in June 2024, the county said. It describes the facility as its first major operations and garage project in 40 years.
The 20-acre site is planned to support buses serving the South Dade TransitWay, according to the county's project page. The county also lists solar components and a reclaimed-water system, along with more than 45 species of native trees, plants and wildflowers.
The county estimates the center will support more than 270 jobs. The estimate describes the planned facility's job impact, not positions confirmed as filled.
The advisory lists Mayor Daniella Levine Cava, Miami-Dade County Commissioner Danielle Cohen Higgins, DTPW Director and CEO Stacy L. Miller, P.E., and DTPW Assistant Director Joel Perez among the participants. It sets media check-in and a tour for 11 a.m., before the 1 p.m. ceremony.