Miami-Dade charges $6.99 per daily gallon for new water, sewer demand
A $100 availability letter shows nearby mains. Capacity certification, water reservations and connection charges decide what a new use costs.
Key Takeaways
- •An informational availability letter establishes no vested right to water or sewer service.
- •A hypothetical 1,000-gallon daily increase brings $6,990 in combined connection charges, before other project costs.
- •Sewer allocation follows the construction permit; water-reservation periods depend on the application pathway.
Miami-Dade County’s water and sewer department charges $1.39 for water and $5.60 for sewer per average daily gallon of connection under the schedule effective Oct. 1.
For a restaurant or salon taking space in the county’s service area, 1,000 added gallons a day would cost $6,990 at those rates, before plumbing and build-out. County Code Section 24-43.1(5) assigns gallons by land use, with separate categories for full-service, fast-food and take-out restaurants.
Three documents and that charge answer four different questions.
- Letter of Availability: Cost or clock: $50 for one service, $100 for both; conditions last 30 days; Question answered: Are mains available?
- Sewer capacity certification: Cost or clock: Initially 90 days to present the letter and submit plans; later follows the active construction permit; Question answered: Can the system take this demand?
- Water supply certification: Cost or clock: 90 days for a no-permit verification or ordinance letter; generally one year when a permit is required; Question answered: Is water reserved for this increase?
- Connection charge: Cost or clock: $1.39 water and $5.60 sewer per daily gallon; Question answered: What does added demand cost?
A letter shows the mains
The county’s Letter of Availability page says the letter advises whether mains can serve a project and gives the developer no vested right to service. The county asks applicants to allow one business day to process the application and invoice; that is not a promised letter-issuance time. Additional information may be needed depending on location and facility size.
Use the exact address and folio. The county’s map shows whether a site falls in a water-only, sewer-only or combined service area. Miami Beach publishes its own utility rates, so a county schedule applies only where the county is the provider.
Capacity runs on another clock
Sewer capacity certification confirms the system can handle the demand tied to a permit, and applicants can seek it before submitting building plans. The initial letter is valid for 90 days; building plans must be submitted within 90 days of the allocation award or the allocation returns to the system. Once linked to an active construction permit, the allocation lasts with that permit and expires if the permit expires.
The water supply program covers new construction and changes that increase consumption. For projects on the one-year building-permit pathway, the applicant must apply for a building permit within that year. The water reservation remains active as long as the building permit is active. Agreement and plat pathways have their own conditions.
Before signing a lease, submit the proposed use and have the architect estimate daily gallons. Price that figure against base rent and build-out on each space under review.
The county’s initial processing step leads to an invoice; applicants must then pay and return proof of payment for the process to continue.